1st Avenue et al

Project Number: 2015133

Construction Estimate: $1,620,000.00

Project Location: 1st Avenue at Erie Street to 1st Avenue and Helena Street; Perry Street at 2nd Avenue to Perry Street and Sprague Avenue; Ivory Street at 2nd Avenue to Ivory Street and Sprague Avenue; Helena Street at 1st Avenue to Helena Street and Sprague Avenue; and Perry Street at 2nd Avenue to Hogan Street and 2nd Avenue.

Description: Provide stormwater conveyance from the area to Pacific and Perry Infiltration Facility. Replace older water distribution lines occurring where storm line installation is occurring. Also includes associated street construction. Funding provided through various sources.

Status: Construction

Contractor: Red Diamond Construction

Project Manager - Design: Jonathan Adams, 509.625.6700, jradams@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2016

Substantially Completed Date: Summer 2016

Award Date: June 6, 2016