Project Number: 2015090
Construction Estimate: $389,000.00
Project Location: Five Mile: East of Five Mile between Strong Road and Heath Avenue; North Hill: Intersection of Garland Avenue and Normandie Street and Intersection of Garland Avenue and Stevens Street; Balboa/South Indian Trail: Woodside Avenue at Alberta Street, Dell Drive and F Street; Emerson Garfield: Northwest Boulevard and Adams Street and Cedar Street south of Alice Avenue, Cedar Street between Dalton Avenue and Alice Avenue, and west side of Cedar Street between Dalton Avenue and Euclid Avenue; West Central: Intersection of Maxwell Avenue and Mission Street and Cedar Street and Maple Street north of Maple Street Bridge; Northwest: Greenwood Street near Olympic Avenue.
Description: Construct street and sidewalk improvements to enhance vehicular and pedestrian traffic safety.
Status: Construction
Contractor: Cameron-Reilly LLC
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Summer 2016
Substantially Completed Date: 05/24/2017
Award Date: September 12, 2016