2016 Residential Grind & Overlay Projects (TBD)

Project Number: 2016044

Construction Estimate: $690,000.00

Project Location:

  • Arthur Street from 39th Avenue to 37th Avenue – District 2
  • Cannon Street from Kiernan Avenue to Garland Avenue – District 1
  • Cedar Street and Madison Street from Boone Avenue to Sharp Avenue – District 3
  • Crestline Avenue and Lea Street from Mission Avemue to Lee Street – District 1
  • Garfield Road from 26th Avenue to Rockwood Boulevard – District 2
  • Perry Street from 2nd Avenue to Sprague Avenue – District 3

Description: Residential grind and overlay pavement preservation project. Work will include minor subgrade repair, crack sealing, modifying ADA ramps, striping and traffic control. Project funded with City of Spokane Transportation Benefit District Funds.

Status: Design

Contractor: To be determined

Project Manager - Design: Rich Proszek, 509.625.6700, rproszek@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2016

Substantially Completed Date: Summer 2016

Award Date: To be determined