2016 Traffic Calming Projects District 1

Project Number: 2016163

Construction Estimate: $200,000.00

Project Location: Various Locations

Description: Sidewalks, curb extensions, crosswalks, etc.

Status: Construction

Contractor: Cameron-Reilly LLC

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2017

Substantially Completed Date: Late Fall 2018

Award Date: May 22, 2017