Project Number: 2017044
Construction Estimate: $900,000.00
Project Location: Crown Avenue – Assembly Street to Alameda Boulevard (District 3); Garfield Road – 29th Avenue to 26th Avenue (District 2); Helena Street – Trent Avenue to Broadway Avenue (District 1) and Gordon Avenue / Pittsburg Street – Helena Street to Crestline Street and Glass Avenue to Empire Avenue (District 1)
Description: Grind and overlay and ADA ramp reconstruction where necessary
Status: Construction
Contractor: Inland Asphalt Company
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Spring 2017
Substantially Completed Date: 10/14/2017
Award Date: July 10, 2017