2018 Residential Grind and Overlay

Description and Location: Contractors will grind pavement at curbs in order to create a bed for new pavement. Then roadways will be overlaid, ADA ramps installed, storm pipes/drains will be installed and patched as needed.

The overlay work will focus on 14 total separate areas throughout the city for 2018.

The work is being performed with city funds. Project number 2018044 is for grind/overlay work on the north half of the City. Project number 2018047 is for grind/overlay work on the south half of the City.

Weekly Meetings:
Each of these two projects (North and South) holds a weekly meeting. A goal of these meeting is to share information, from City/Contractor staff to you, and to receive information from you. It is our hope that through timely and thoughtful information sharing, emerging concerns are addressed as quickly and directly as possible. See specific weekly meeting time under the appropriate project drop down below.

Construction Information:

Residential Grind and Overlay (North)

Weekly Meeting Day/Time/Location: Weekly meetings for this project will be held at different locations (depending upon where the focus of the work is occurring). The first meeting will be July 16, at 2:00 p.m. Please contact Jared Boucher at 509-536-3094 for location.

Project Number: 2018044

Construction Estimate: $2,335,000

Status: Construction

Contractor: Inland Asphalt

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: July 2018

Substantially Completed Date: Fall 2018

Award Date: May 21, 2018

Residential Grind and Overlay (South)

Weekly Meeting Day/Time/Location:
Thursdays 8:00 – 9:00 A.M.
Southside Senior and Community Center
3151 E 27th, Spokane

Project Number: 2018047

Construction Estimate: $2,990,000.00

Status: Construction

Contractor: Shamrock Paving

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2018

Substantially Completed Date: Fall 2018

Award Date: Bid Opening June 25, 2018


Contact Information

Residential Grind and Overlay (North) Contact

Jared Boucher
Public Liaison
Inland Asphalt
509.536.3094

Residential Grind and Overlay (South) Contact

Tawny Thompson
Public Liaison
Shamrock/Murphy Brothers
509.385.3303
Tawny@shamrockpaving.us

General Contact

Michele Vazquez
City of Spokane
Construction Relations Manager
509.625.6102