Description and Location: Contractors will grind pavement at curbs in order to create a bed for new pavement. Then roadways will be overlaid, ADA ramps installed, storm pipes/drains will be installed and patched as needed.
The overlay work will focus on 14 total separate areas throughout the city for 2018.
The work is being performed with city funds. Project number 2018044 is for grind/overlay work on the north half of the City. Project number 2018047 is for grind/overlay work on the south half of the City.
Weekly Meetings:
Each of these two projects (North and South) holds a weekly meeting. A goal of these meeting is to share information, from City/Contractor staff to you, and to receive information from you. It is our hope that through timely and thoughtful information sharing, emerging concerns are addressed as quickly and directly as possible. See specific weekly meeting time under the appropriate project drop down below.
Construction Information:
Weekly Meeting Day/Time/Location: Weekly meetings for this project will be held at different locations (depending upon where the focus of the work is occurring). The first meeting will be July 16, at 2:00 p.m. Please contact Jared Boucher at 509-536-3094 for location.
Project Number: 2018044
Construction Estimate: $2,335,000
Status: Construction
Contractor: Inland Asphalt
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: July 2018
Substantially Completed Date: 10/22/2018
Award Date: May 21, 2018
Weekly Meeting Day/Time/Location:
Thursdays 8:00 – 9:00 A.M.
Southside Senior and Community Center
3151 E 27th, Spokane
Project Number: 2018047
Construction Estimate: $2,990,000.00
Status: Construction
Contractor: Shamrock Paving
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Summer 2018
Substantially Completed Date: 10/24/2018
Award Date: Bid Opening June 25, 2018
Jared Boucher
Public Liaison
Inland Asphalt
509.536.3094
Tawny Thompson
Public Liaison
Shamrock/Murphy Brothers
509.385.3303
Tawny@shamrockpaving.us
Michele Vazquez
City of Spokane
Construction Relations Manager
509.625.6102