2018 Street Maintenance Grind and Overlay

Descripton: Street Maintenance Crews will grind the roadway and overlay it to provide a new pavement surface.

Locations: The grind & overlay work will focus on 7 separate areas throughout the city for 2018.

Current Projects/Areas

All projects/areas have been completed.

Completed Projects/Areas
  • Wellesley Av – Division to Nevada: Completed May 2018
  • Assembly – Olympic to Rowan: Completed June 2018
  • Altamont – Hartson to Sprague: Completed June 2018
  • Southeast Bl – Regal to 29th: Completed July 2018
  • Freya St – 29th to Hartson: Completed August 2018
  • Cedar/Maple/Walnut – 21st to 9th: Completed October 2018
  • Palouse Hy – Freya to Regal: Completed October 2018

Status: Construction

Construction By: City Street Department

Start Date: Spring 2017

Completion Date: Fall 2018


Contact Information

Street Department Contact

Ron Howerton
Street Supervisor
509.625.7741
rhowerton@spokanecity.org

Construction Relations Manager

Michele Vazquez
Construction Relations Manager
509.625.6102
mvazquez@spokanecity.org