Project Number: 2019044
Contractor Bid: $1,395,309.60
Project Location: Various Locations
Description: Grind and overlay and ADA ramp reconstruction where necessary. Project funded with local funds.
Status: Construction
Contractor: Shamrock Paving, Inc.
Project Manager – Construction: Construction Management, 509.625.7722
Construction Start Date: 7/15/2019
Substantially Completed Date: 10/17/2019
Award Date: June 17, 2019
Information Last Updated: August 8, 2019
Tawny Thompson
Public Liaison, Shamrock Paving
Phone: 509.385.3303
Email: tawny@shamrockpaving.us
Michele Vazquez
Construction Relations Manager
City of Spokane
mvazquez@spokanecity.org