2021 Arterial Chip Seal - Economic Recovery Project

Project Number: 2021086

Construction Estimate: $500,000

Project Locations and Schedule:

  • North Freya Street from East Upriver Drive to East Wellesley Avenue
    • Chip seal date (tentative): August 4th
  • South Freya Street from East 37th Avenue to South Palouse Highway
    • Chip seal date (tentative): August 5th
  • North Post Street from West Cleveland Avenue to West Maxwell Avenue
    • Chip seal date (tentative): August 2nd
  • South Southeast Boulevard from South Perry Street to East 29th Avenue
    • Chip seal date (tentative): August 6th
  • Wellesley Avenue from Milton Street to Ash Street
    • Chip seal date (tentative): August 3rd

On the day the contractor chip seals, the road will be closed to through traffic from 6:00 a.m. to 4:00 p.m. Cars parked on the road will be towed in order to complete the work. For each location, the contractor will send notification by mail two business days in advance to residents listing the exact date of the chip seal.

Description: Apply chip seal to preserve pavement life.

Status: Awarded

Contractor: Shamrock Paving, Inc.

Project Manager - Design: Rich Proszek, 509.625.6907, rproszek@spokanecity.org

Project Manager - Construction: Kelly Heitstuman, 509.625.7722, kheitstuman@spokanecity.org

Construction Start Date: July 12, 2021

Expected Completion Date: August 10, 2021

Award Date: May 24, 2021


Contact Information

For questions or concerns regarding the construction work, please contact the contractor’s public representative:
Talia Brestar
509.638.3443
talia.b@shamrockpaving.us

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane's Construction Relations Manager:
Karin Janssen
509.625.6102
kjanssen@spokanecity.org

Related Links