2021 Arterial Grind and Overlay – Economic Recovery Project

Project Number: 2021064

Construction Estimate: $1,000,000

Project Location: Garland/Empire Avenue from Crestline Street to Market Street, Belt Street from Boone Avenue to Maxwell Avenue

Description:Grind and overlay of arterial streets. This project is funded with local funds.

Status: Design

Contractor: To be determined

Project Manager - Design: Jake Dial, 509.625.6907, jdial@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2021

Substantially Completed Date: Fall 2021

Award Date: To be determined

In order to preserve pavement life, the City of Spokane's Pavement Cut Policy is in effect for all street-related projects.