2021 Arterial Grind and Overlay – Economic Recovery Project

Project Number: 2021064

Status: Substantially complete

Construction Estimate: $1,000,000

Project Description: Grind and overlay of arterial streets. This project is funded with local funds.

Project Location(s) and Schedule*

  • Garland/Empire Avenue - Crestline Street to Market Street
  • Belt Street - Boone Avenue to Maxwell Avenue

*Crews will be in the area during this time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Contractors are responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business days' notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: Yes:Empire/Garland. View detour map (PDF 413 KB)
  • Planned Lane Restrictions: Yes
  • Planned Road Closures: Yes:
    • Empire/Garland closed to through traffic October 11 to November 11
    • Belt Street closed to through traffic September 20 to October 8
  • Planned Utility Work: No
  • Pavement Cut Policy In Effect: Yes

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily restrict traffic. For everyone's safety, please obey all traffic signs.

Construction Start Date: September 27, 2021

Construction Completed Date: October 29, 2021

Contract Award Date: August 16, 2021

Contractor: Inland Asphalt Company

City Project Manager - Construction Phase: Ryan Schulte, 509.625-7722, rschulte@spokanecity.org

City Project Manager - Design Phase: Jake Dial, 509.625.6700, eraea@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor’s public representative:
Mike Simpson
509.703.8772

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or eraea@spokanecity.org.

Related Links