2021 Residential Chip Seal

Project Number: 2021043

Status: Construction

Construction Estimate: $1,000,000

Description: Apply chip seal to preserve pavement life. This project is funded with local funds.

Project Location(s) and Schedule*:

  • Pittsburg Street from Wellesley Avenue to Francis Avenue: 7/21–9/16. View map (PDF 933 KB)
  • Woodside Avenue from Indian Trail Road to Lindeke Street: 7/20–9/16. View map (PDF 885 KB)
  • F Street and Woodland Boulevard: 7/15–9/16. View map (PDF 945 KB)

*Crews will be in the area during this time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Contractors are required to provide two business-day notice to a homeowner if the homeowner’s property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: Yes
  • Planned Lane Restrictions: Yes
  • Planned Road Closures: Yes
  • Planned Utility Work: No
  • Pavement Cut Policy In Effect: Yes

Note, the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily restrict traffic. For everyone's safety, please obey all traffic signs.

Construction Start Date: 7/15/2021

Construction Completion Date: 8/30/2021

Contract Award Date: 5/24/2021

Contractor: Shamrock Paving, Inc.

City Project Manager - Construction Phase: Mark Melnick, 509.625.7722, mmelnick@spokanecity.org

City Project Manager - Design Phase: Rich Proszek, 509.625.6907, rproszek@spokanecity.org


Contact Information

For questions or concerns regarding the construction work, please contact the contractor’s public representative:
Talia Brestar
509.638.3443
talia.b@shamrockpaving.us

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane's Construction Relations Manager:
Karin Janssen
509.625.6102
kjanssen@spokanecity.org

Related Links