2021 Street Maintenance Curb Ramps

Project Number: 2020042

Construction Estimate: $500,000

Description: This project consists of installing curb ramps on streets where the Street Department has or will be doing grind and overlay work. This project is funded with local funds.

Status: Design

Contractor: Cameron-Reilly LLC

Project Manager - Design: Rich Proszek, 509.625.6700, rproszek@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2021

Substantially Completed Date: Summer 2021

Award Date: January 4, 2021

Project Locations
  • Broadway & Cannon – northwest, northeast, southwest, and southeast corners
  • Broadway & Elm – northwest and southwest corners only
  • Garland & Belt – northwest and northeast corners only
  • Garland & Cannon – northwest, northeast, and southwest corners only
  • Garland & Elgin – northwest and southwest corners only
  • Garland & Elm – northwest, northeast, and southwest corners only
  • Hamilton & Boone – northwest, northeast, and southeast corners only
  • Hamilton & Sinto – northwest, northeast, southwest, and southeast corners
  • Hamilton & August – northwest, northeast, and southeast corners only
  • Hamilton & Nora – northwest, northeast, southwest, and southeast corners
  • Hamilton & Baldwin – northwest, northeast, southwest, and southeast corners
  • Hamilton & Ermina – northwest, northeast, southwest, and southeast corners
  • Hamilton & Montgomery – northwest, northeast, and southeast corners only
  • Hamilton & Carlisle – northwest, northeast, southwest, and southeast corners
  • Hamilton & Jackson – northwest, northeast, southwest, and southeast corners
  • Hamilton & Marietta – northeast, southwest, and southeast corners only
  • Havana & Hartson – northeast corner only
  • Hartson & Rebecca – southeast corner only
  • Havana & 5th – northwest and southwest corners only
  • Howard & Cataldo – northeast and southeast corners only
  • Howard & Dean – northwest, northeast, and southeast corners only
  • Howard & Gardner – west and east side of Howard
  • Howard & Mallon – northwest corner only
  • Howard & Sharp – northeast, southwest, and southeast corners only
  • Illinois & Hogan – northwest, northeast, and southeast corners only
  • Illinois & Madelia – northwest, northeast, and southwest corners only
  • Illinois & Magnolia – northeast corner only
  • Illinois & Napa – northwest corner only
  • Rowan & Addison – northeast corner only
  • Rowan & Bemis – northwest, northeast, and southwest corners only
  • Rowan & Cincinnati – northwest, northeast, and southeast corners only
  • Rowan & Standard – northwest corner only

In order to preserve pavement life, the City of Spokane's Pavement Cut Policy is in effect for all street-related projects.

Other Improvement Projects for the Hamilton Corridor in 2021

The City will coordinate the following additional improvement projects in 2021:

  • Street Department Grind and Overlay: Hamilton Street from Desmet to North Foothills. The Street Department will resurface Hamilton Street. Lane reductions will occur during the work. Work is expected to take two months.
  • Project 2010056 Hamilton Corridor Safety Improvements. This project will implement safety and traffic flow improvements at six intersections, including the addition of dedicated left turn signals. The signal work on Indiana and Hamilton and North Foothills and Hamilton will be completed in the 2021 construction season. Work is expected to take three months.
  • Project 2018143 2021 Spokane Street Preservation North Phase 2. The City will chip seal Nevada from Francis to North Foothills. Lane reductions will occur during the work. Work is expected to take one month.

Contact Information

Karin Janssen
Construction Relations Manager
kjanssen@spokanecity.org