2nd & 3rd Avenue Stormwater Piping

Project Number: 2016199

Contractor Bid: $1,774,634.94

Project Location:

  • 2nd avenue from Hamilton Street overpass to Perry Street
  • 3rd Avenue from Hatch Street to Arthur Street

Description: Installation of storm water piping.

Status: Construction

Contractor: Halme Construction, Inc.

Project Manager – Design: Duane Studer, 509.625.6700, dstuder@spokanecity.org

Project Manager – Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2019

Substantially Completed Date: Fall 2019

Award Date: February 25, 2019

Information Last Updated: March 26, 2019