37th Avenue Sidewalk, Manito Boulevard to Latawah Street

Project Number: 2019096

Construction Estimate: $261,504

Project Location: 37th Avenue, Manito Boulevard to Latawah Street

Description: Construct 6-foot sidewalk on south side of 37th Avenue, to include ADA curb ramps and storm drain modifications as required. Project is funded with local and state funds.

Status: Complete

Contractor: Bacon Concrete, Inc

Project Manager - Design: Rich Proszek, 509.625.6700, rproszek@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: May 4, 2020

Substantially Completed Date: June 2020

Award Date: November 2019

37th Avenue Sidewalk, Manito Boulevard to Latawah Street

Project Number: 2019096

Construction Estimate: $261,504

Project Location: 37th Avenue, Manito Boulevard to Latawah Street

Description: Construct 6-foot sidewalk on south side of 37th Avenue, to include ADA curb ramps and storm drain modifications as required. Project is funded with local and state funds.

Status: Completed

Contractor: Bacon Concrete, Inc

Project Manager - Design: Rich Proszek, 509.625.6700, rproszek@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: May 4, 2020

Substantially Completed Date: June 2020

Award Date: November 2019


Construction Meeting Updates

June 25, 2020
June 18, 2020
June 04, 2020
May 20, 2020
May 14, 2020

Construction Meeting Updates