Arterial Curb Ramp Projects - North

Project Number: 2019042

Construction Estimate: $1,052,237

Project Locations
  • North Foothills Drive and Buckeye Avenue
  • North Foothills Drive and Standard Street
  • North Foothills Drive and Dakota Street
  • Freya Street and Montgomery Avenue
  • Freya Street and Carlisle Avenue
  • Freya Street and Marietta Avenue
  • Freya Street and Buckeye Court (East)
  • Freya Street and Grace Avenue
  • Freya Street and Cleveland Avenue
  • Freya Street and Fairview Avenue
  • Freya Street and Euclid Avenue
  • Freya Street and Liberty Avenue
  • Freya Street and Bridgeport
  • Freya Street and Courtland Avenue
  • Freya Street and Garnet Avenue
  • Freya Street and Glass Avenue
  • Freya Street and Gordon Avenue
  • Hamilton Street and Springfield Avenue
  • Hamilton Street and Cataldo Avenue
  • Indiana Avenue and Lincoln Street
  • Indiana Avenue and Wall Street
  • Indiana Avenue and Stevens Street
  • Indiana Avenue and Calispel Street
  • Indiana Avenue and Normandie Street
  • Indiana Avenue and Atlantic Street
  • Indiana Avenue and Springfield Avenue
  • Indiana Avenue and Cataldo Avenue
  • Nevada Street and Sharpsburg Avenue
  • Nevada Street and Calkins Drive
  • Nevada Street and St. Thomas Moore Way (West)
  • Nevada Street and St. Thomas Moore Way (East)
  • Nevada Street and Vicksburg Avenue
  • Northwest Boulevard and Walnut Avenue / Montgomery Street
  • Northwest Boulevard and Mansfield Avenue (South)
  • Northwest Boulevard and Cedar Street / Mansfield Avenue
  • Northwest Boulevard and Knox Avenue / Adams Street
  • Northwest Boulevard and Knox Avenue (North)
  • Northwest Boulevard and Jefferson Street
  • Northwest Boulevard and Shannon Avenue
  • Northwest Boulevard and Shannon Avenue / Madison Street
  • Northwest Boulevard and Shannon / Madison (Median)
  • Post Street and Sinto Avenue
  • Wall Street and Walton Avenue
  • Wall Street and Lacrosse Avenue
  • Wall Street and Rockwell Avenue
  • Wall Street and Longfellow Avenue
  • Wall Street and Heroy Avenue
  • Wall Street and Princeton Avenue
  • Wellesley Avenue and Morton Street
  • Wellesley Avenue and Perry Street
  • Wellesley Avenue and Helena Street
  • Wellesley Avenue and Pittsburg Street
  • Wellesley Avenue and Magnolia Street
  • Wellesley Avenue and Napa Street (South)
  • Wellesley Avenue and Napa Street (North)
  • Wellesley Avenue and Martin Street
  • Wellesley Avenue and Lee Street
  • Wellesley Avenue and Stone Street
  • Wellesley Avenue and Altamont Street
  • Wellesley Avenue and Cook Street
  • Wellesley Avenue and Smith Street
  • Wellesley Avenue and Lacey Street
  • Wellesley Avenue and Nelson Street
  • Wellesley Avenue and Regal Street

Description: Update curb ramps for ADA compliance on streets where the street department has done grind and overlay projects. Project is funded with local funds.

Status: Complete

Contractor: Cameron-Reilly LLC

Project Manager - Design: Rich Proszek, 509.625.6700, rproszek@spokanecity.org

Project Manager - Construction: Mike Zangara, 509.625.7722

Construction Start Date: May 4, 2020

Substantially Completed Date: August 1, 2020

Award Date: April 6, 2020

To reduce pavement degradation, the City of Spokane's Pavement Cut Policy is in effect for all street-related projects.