Ben Burr Crossings at 2nd/Perry & 3rd/Perry

Project Number: 2019106

Construction Estimate: $363,288.75

Project Location: Ben Burr Trail

Description: Crosswalk safety enhancements at Perry/2nd and Perry/3rd Avenues. This project is funded by local, state, and federal funds.

Status: Construction

Contractor: Power City Electric

Project Manager - Design: Jake Dial, 509.625.6700, jdial@spokanecity.org

Project Manager - Construction: Ryan Schulte, 509.625.7722

Construction Start Date: September 2020

Substantially Completed Date: October 2020

Award Date: 08/17/2020