Project Number: 2019106
Construction Estimate: $363,288.75
Project Location: Ben Burr Trail
Description: Crosswalk safety enhancements at Perry/2nd and Perry/3rd Avenues. This project is funded by local, state, and federal funds.
Status: Construction
Contractor: Power City Electric
Project Manager - Design: Jake Dial, 509.625.6700, jdial@spokanecity.org
Project Manager - Construction: Ryan Schulte, 509.625.7722
Construction Start Date: September 2020 (this project is currently on hold due to supply chain issues and is expected to be completed this winter)
Substantially Completed Date: January 2021 (estimated)
Award Date: 08/17/2020