Central Avenue Well #2 Rehabilitation

Project Number: 2016133

Construction Estimate: $995,429.30

Project Location: Central Avenue and Normandie Street

Description: Station to be upgraded and mondernized with a new building housing a single pump and motor. Project funded with federal funds.

Status: Construction

Contractor: T. LaRiviere Equipment and Excavation

Project Manager - Design: Dan Buller, 509.625.6700, dbuller@spokanecity.org

Construction Start Date: Summer 2018

Substantially Completed Date: Spring 2019

Award Date: January 8 2017