Project Number: 2016081
Construction Estimate: $567,428
Project Location: Cincinnati Street from Spokane Falls Boulevard to Euclid Avenue
Description: Add greenway elements to Cincinnati Street that encourages non-motorized modes of transportation.
Status: Construction
Contractor: NNAC
Project Manager - Design: Dan Buller, 509.625.6700, dbuller@spokanecity.org
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: May 4, 2020
Substantially Completed Date: July 2020
Award Date: August 2019
To reduce pavement degradation, the City of Spokane's Pavement Cut Policy is in effect for all street-related projects.