Project Number: 2014117
Construction Estimate: $1.2 million
Project Location: High Drive from Browne Street to Hatch Road
Description: This project will construct three Combined Sewer Overflow (CSO) storage facilities with an in-line storage configuration. This project will be constructed as part of the High Drive project. This project is being funded with Wastewater funds
Status: Design
Contractor: To be determined
Project Manager - Design: Jonathan Adams, 509.625.6700, jradams@spokanecity.org
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Spring 2015
Substantially Completed Date: Fall 2015
Award Date: To be determined