Combined Sewer Overflow (CSO) Basin 33-2 Control Facility – East U District

Project Number: 2011085

Construction Estimate: $3.7 million

Project Location: East downtown Spokane across from the City's Sewer Maintenance Facility which is located at 909 East Sprague Avenue

Description: This project will construct a combined sewer overflow facility on City property across from the City's Sewer Maintenance Facility (909 East Sprague Avenue). This project is being funded by the Wastewater Management Department.

Status: Design

Contractor: Garco Construction

Project Manager - Design: Dan Buller, 509.625.6700, dbuller@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2014

Substantially Completed Date: Summer 2015

Award Date: December 16, 2013