CSO 6 Control Facility – Phase 2

Project Number: 2010075

Construction Estimate: $1,667,432.00

Project Location: Northwest Boulevard and H Street south to Columbia Circle and H Street west and south to Downriver Drive and Columbia Circle

Description: Sewer main installation and street reconstruction from Northwest Boulevard and H Street south to Columbia Circle and H Street west and south to Downriver Drive and Columbia Circle

Status: Construction

Contractor: MDM Construction, Inc.

Project Manager - Design: Cindy Kinzer, 509.625.6700, ckinzer@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: July 2015

Substantially Completed Date: Fall 2015

Award Date: June 16, 2015