CSO Basin 23 Control Facility

Project Number: 2010076

Construction Estimate: $1,000,000.00

Project Location: 37th Avenue between Regal Street and Custer Street

Description: Construction of 38,000 gallon storage tank in Ash Street near the intersection with Bridge Avenue (CSO 23-2) and 13,000 gallon storage tank in Cedar Street near the intersection with Summit Parkway.

Status: Design

Contractor: To be determined

Project Manager - Design: Duane Studer, 509.625.6176, dstuder@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2018

Substantially Completed Date: Summer 2018

Award Date: To be determined