CSO Basin 24 Control Facility

Project Number: 2010087

Construction Estimate: $16,300,000.00

Project Location: Near the intersection of 1st Avenue and Adams Street

Description: Construction of a 2.3 million gallon CSO tank

Status: Construction

Contractor: Halme

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2017

Substantially Completed Date: Winter 2018

Award Date: To be determined