CSO Basin 26 Control Facility

CSO 26 Time-lapse (Monroe)

CSO 26 Time-lapse (Spokane Falls Blvd)

Project Number: 2010088

Construction Estimate: $22,000,000.00

Project Location: Spokane Falls Boulevard from Monroe Street to Lincoln Street

Description: Construction of a 2 MG CSO tank and associated plaza above proposed tank. Project funded with state and local funds.

Status: Construction

Contractor: Garco Construction

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2017

Substantially Completed Date: Fall 2018

Award Date: April 11, 2016