Project Number: 2010088
Construction Estimate: $29,000,000
Project Location: Spokane Falls Boulevard from Monroe Street to Lincoln Street
Description: Construction of a flow control chamber on Lincoln St. between Main St. and Spokane Falls Blvd. Project funded with state and local funds.
Status: Construction
Contractor: Garco Construction
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Summer 2020
Substantially Completed Date: September 28, 2020
Award Date: April 11, 2016
To reduce pavement degradation, the City of Spokane's Pavement Cut Policy is in effect for all street-related projects.