CSO Basin 41 Control Facility

Project Number: 2010102

Construction Estimate: $$875,000.00

Project Location: Intersection of Upriver Drive and Rebecca Street; Approximately 300’ west of Upriver Drive and Freya Street intersection.

Description: Construct 380,000 gallon, 60” pipe CSO facility and associated piping.

Status: Construction

Contractor: N & N Excavation LLC

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2017

Substantially Completed Date: Fall 2017

Award Date: August 30, 2016