Project Number: 2014057
Construction Estimate: $598,000
Project Location: Division Street and 3rd Avenue; Division Street and 4th Avenue
Description: Design and construct aesthetic and functional streetscape improvements including landscaping, irrigation, walls, fencing/screening, original art or sculpted art elements and miscellaneous hardscape features. Intersection improvements may consist of special paving at crosswalks, trees and lighting, as well as conduit needs and possible signal upgrades. This project is being funded with State and Federal funds.
Status: Construction
Contractor: Bacon Concrete, Inc.
Project Manager - Design: Dan Buller, 509.625.6700, dbuller@spokanecity.org
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Spring 2015
Substantially Completed Date: Spring 2015
Award Date: December 15, 2014