Erie Stormwater Facility from Front Avenue to Trent Avenue

Project Number: 2015130

Construction Estimate: $1,200,000.00

Project Location: Erie Street from Front Avenue to Trent Avenue

Description: Provide stormwater runoff storage and water quality improvements. Project funded with local funds.

Status: Design

Contractor: To be determined

Project Manager - Design: Duane Studer, 509.625.6700, dstuder@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2019

Substantially Completed Date: Fall 2019

Award Date: To be determined