Project Number: 2015130
Contractor Bid: $2,139,999.99
Project Location: Erie Street from Front Avenue to Trent Avenue
Description: Provide stormwater runoff storage and water quality improvements. Project funded with local funds.
Status: Construction
Contractor: DW Excavating, Inc.
Project Manager – Design: Duane Studer, 509.625.6700, dstuder@spokanecity.org
Project Manager – Construction: Construction Management, 509.625.7722
Construction Start Date: Summer 2019
Substantially Completed Date: Fall 2019
Award Date: June 10, 2019
Information Last Updated: July 9, 2019
Lars Hendrickson
Public Liaison
DW Excavating
Phone: 509.919.7659
Lars@dwexcavating.net
Michele Vazquez
Construction Relations Manager
City of Spokane
mvazquez@spokanecity.org