Five Mile Booster Station from Belt Street to Woodside Avenue

Project Number: 2017104

Construction Estimate: $1,500,000.000

Project Location: Five Mile Booster Station from Belt Street to Woodside Avenue

Description: The construction of a new booster station located east of the existing station designed with the ability to add additional capacity for future growth. Funded with local funds.

Status: Design

Contractor: T. LaRiviere Equipment and Excavation

Project Manager - Design: Cindy Kinzer, 509.625.6700, ckinzer@spokanecity.org

Construction Start Date: Spring 2018

Substantially Completed Date: Fall 2019

Award Date: January 8 2017