Geiger Boulevard Phase 2 from Soda Road to Grove Road

Project Number: 2019167

Construction Estimate: $1,000,000

Project Location: Geiger Blvd from Soda Rd to Grove Rd

Description: Water and sewer main installation.

In order to preserve the street life by minimizing the impact of pavement cuts, the City of Spokane, Spokane County and the City of Spokane Valley, in coordination with public and private area utilities, together adopted a regional pavement cut policy. Although there are nuances to this policy, it generally places a 3-year moratorium on future pavement cuts following pavement construction or reconstruction.

The City of Spokane's Pavement Cut Policy applies for this project. More information.

Status: Design

Contractor: To be determined

Project Manager - Design: Jake Dial, 509.625.6700, jdial@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2020

Substantially Completed Date: Spring 2020

Award Date: To be determined