Project Number: 2019067
Construction Estimate: $790,000.00
Project Location: Geiger Boulevard from Hayford Road to Soda (water toward the west end, sewer toward the east end)
Description: Water and sewer installation within Geiger Boulevard to serve adjacent properties. Project funded with federal and local funds.
Status: Design
Contractor: To be determined
Project Manager – Design: Cindy Kinzer, 509.625.6700, ckinzer@spokanecity.org
Project Manager – Construction: Construction Management, 509.625.7722
Construction Start Date: Summer 2019
Substantially Completed Date: Planned Summer 2019
Award Date: To be determined