Project Number: 2018085
Status: Construction
Construction Estimate: $1,931,822
Project Description: Replace the existing bridge deck. This project is funded with federal funds.
Project Location(s) and Schedule
Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.
Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.
Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.
Construction Zone Details
Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.
Expected Construction Start Date: March 29, 2022
Expected Construction Completed Date: July 31, 2022
Contract Award Date: October 25, 2021
Contractor: Halme Construction, Inc.
City Project Manager - Construction Phase: Mike Zangara, 509.625.7722, mzangara@spokanecity.org
City Project Manager - Design Phase: Jonathan Adams, 509.625.6700, jradams@spokanecity.org
If you would like to sign up for weekly project updates, please email Wyatt Newhouse at wyattn@halmeconstruction.onmicrosoft.com.
For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
Wyatt Newhouse
Halme Construction
509.934.0193 (mobile)
If the contractor's public representative cannot resolve your issue, please contact the City of Spokane's Construction Relations Manager:
Karin Janssen
509.625.6102
kjanssen@spokanecity.org