Hazel's Creek Downstream Conveyance from Hazel's Creek Pond to Cuba Street

Project Number: 2013055

Construction Estimate: $1,600,000.00

Project Location: Southeast of 37th Avenue and Rebecca Street

Description: Construct stormwater treatment and disposal ponds and associated stormwater piping. The system will be an extension of the existing Hazel’s Creek Facility on 42nd Avenue.

Status: Construction

Contractor: Schimmels Construction

Project Manager - Design: Rich Proszek, 509.625.6700, rproszek@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2016

Substantially Completed Date: Summer 2016

Award Date: March 7, 2016