Indiana Avenue from Dakota Street to Perry Street Phase II

Project Number: 2014150

Construction Estimate: $2,000,000.00

Project Location: Indiana Avenue from Division Street to Perry Street and North Crescent Street from Indiana Avenue to the north approximately 160 feet.

Description: Full depth replacement of 7,500 feet of roadway including new curb ramps, swale/storm garden area, new curb, replacement of water line, replacement/installation of signal loops and removal of approximately 70 parking spaces.

Status: Design

Contractor: To be determined

Project Manager - Design: Dan Buller, 509.625.6700, dbuller@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2016

Substantially Completed Date: Fall 2016

Award Date: To be determined