Interceptor I-07c Riverside Control Facility

Project Number: 2014096

Construction Estimate: $2,800,000.00

Project Location: Near the intersection of Riverside Avenue and Napa Street intersection

Description: Construction of 200,000 gallon CSO tank

Status: Construction

Contractor: Max J Kuney Company

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2017

Substantially Completed Date: Spring 2018

Award Date: June 19, 2017