Main Avenue / Division Street Intersection Improvements

Project Number: 2011103

Construction Estimate: $442,359.00

Project Location: Division Street from East MLK Jr. Way to East Spokane Falls Boulevard; East Main Avenue from North Brown Street to North Pine Street

Description: Install "bumpouts" at all four corners of Division Street / Main Avenue intersection. Remove and replace existing curb/gutter and sidewalk including ADA upgrades. Install new planter boxes/plantings. Funding provided by the 2015 Pedestrian/Bicycle funding.

Status: Construction

Contractor: Arc Electric

Project Manager - Design: Dan Buller, 509.625.6700, dbuller@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2016

Substantially Completed Date: Spring 2016

Award Date: November 17, 2015