Project Number: 2012115
Construction Estimate: $3.8 million
Project Location: Monroe Street and Lincoln Street from 8th Avenue to Main Avenue
Description: Full depth roadway replacement, curb and sidewalk revisions, including ADA curb ramp installations. Pedestrian lighting will be installed. This project is being funded with Federal funds.
Status: Construction
Contractor: Murphy Brothers
Project Manager - Design: Jonathan Adams, 509.625.6700, jradams@spokanecity.org
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Summer 2015
Substantially Completed Date: Fall 2015
Award Date: July 14, 2015
Thursdays
2-3 p.m.
Deaconess Hospital, 800 W. 5th Avenue