Panorama Drive Water Main Replacement

Project Number: 2014075

Construction Estimate: $965,000

Project Location: Panorama Drive from Panorama Avenue to Carolina Way, Maple Street from Cascade Way to Sierra Way, Cascade Way from Maple Street to Panorama Drive and Sierra Way from Maple Street to Panorama Drive

Description: This project will replace cast iron distribution mains and repave the entire street. This project is funded with City Water funds.

Status: Construction

Contractor: Red Diamond Construction, Inc.

Project Manager - Design: Jonathan Adams, 509.625.6700, jradams@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2015

Substantially Completed Date: Summer 2015

Award Date: May 4, 2015