Project Number: 2017105

Construction Estimate: $13,000,000.00

Project Location: Post Street Bridge

Description: Post Street bridge replacement. Project funded with federal funds.

Status: Construction

Contractor: Halme Construction, Inc.

Project Manager - Design: Mark Serbousek, 509.625.6700, mserbousek@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Fall 2018

Substantially Completed Date: Winter 2020

Award Date: To be determined