Project Number: 2012116
Construction Estimate: $687,000
Project Location: Ray Street from 29th Avenue to 17th Avenue
Description: Apply preservation treatments that may consist of crack sealing, grind and overlay or other pavement rejuvenation techniques. Upgrades to ADA curb ramps and minor curb and sidewalk repairs are anticipated. This project is being funded with Federal Surface Transportation Program funding.
Status: Construction
Contractor: Inland Asphalt Company
Project Manager - Design: John Miller, 509.625.6700, jmiller@spokanecity.org
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Summer 2015
Substantially Completed Date: Fall 2015
Award Date: August 11, 2015