Spokane Street Preservation North, Phase 1

Project Number: 2017148

Contractor Bid: $2,422,422.00

Project Description and Approximate Schedule: The city of Spokane is planning to rehabilitate four streets spread across the city. These projects will update the existing pavement surface by grinding the existing pavement down and overlaying it with new asphalt. Wheelchair ramps will be brought into ADA compliance and minor storm sewer upgrades and/or repairs will also be included in the project. Please see below for project limits and their approximate schedules.

Spring & Summer 2019 – Sprague Avenue

  • Sprague (Scott to Helena): Project starts April 1, 2019
  • Maple/Ash streets (Rowan to Country Holmes Blvd): Project starts May 20, 2019
  • Wellesley Avenue (Driscoll Blvd to Milton St)

Information for Local Residents/Property Owners and Businesses:

  • Special Access Requirements
    We are very interested in working with you to reduce the construction impact. If you have special access needs, such as business needs, personal medical issues or disability access needs, please contact Adriene Turner at the email address or phone number on the right hand side of this page.

Status: Completed

Contractor: Inland Asphalt Company

Project Manager – Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2019

Substantially Completed Date: 09/03/2019

Award Date: December 17, 2018

Information Last Updated: November 12, 2019