Project Number: 2013221
Construction Estimate: $1.1 Million
Project Location: Various locations in the vicinity of Trent Avenue and Helena Street
Description: Construct stormwater treatment and disposal facilities (swales and similar facilities.) This project is being funded State and local funds.
Status: Construction
Contractor: L & L Cargile, Inc.
Project Manager - Design: Jonathan Adams, 509.625.6700, jradams@spokanecity.org
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Fall 2015
Substantially Completed Date: Winter 2015
Award Date: September 17, 2015