University District Pedestrian/Bicycle Bridge

Project Number: 2012119

Construction Estimate: $9,400,000.00

Project Location: Approximately Sherman Avenue from WSU campus to Riverside Avenue

Description: Pedestrian Bridge

Status: Construction

Contractor: Garco Construction

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2017

Substantially Completed Date: Spring 2018

Award Date: January 9, 2017