Wellesley/Maple Intersection

Project Number: 2019107

Status: Complete

Construction Estimate: $500,000

Project Description: To improve traffic flow, the westbound left turn lane will be lengthened by approximately one block via island modifications between Maple Street and Walnut Street. This project is funded with state and local funds.

Project Location(s) and Schedule*
Intersection of Wellesley Avenue and Maple Street.

  • Demo work: 9/7 – 9/10
  • Signal work: 9/11 – 9/13
  • Roadway and concrete work: 9/15 – 10/1
  • Avista night work 9/23 – 9/26
  • Grind and overlay 10/4 – 10/6
  • Road striping and signage 9/28 – 9/30
  • Suspension of work for PCCP curing 9/29 – 10/23
  • Permanent road striping 11/15

*Crews will be in the area during this time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Contractors are responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor’s public representative.

Contractors are required to provide two business-day notice to a homeowner if the homeowner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: No
  • Planned Lane Restrictions: Yes
  • Planned Road Closures: Possibly one weekend closure
  • Planned Utility Work: Electrical
  • Pavement Cut Policy In Effect: Yes

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily restrict traffic. For everyone's safety, please obey all traffic signs.

Construction Start Date: September 7, 2021

Construction Completed Date: October 28, 2021

Contract Award Date: June 7, 2021

Contractor: Corridor Contractors

City Project Manager - Construction Phase: Kelly Heitstuman, 509-625-6700, kheitstuman@spokanecity.org

City Project Manager - Design Phase: Jonathan Adams, 509.625.6700, jradams@spokanecity.org


Contact Information

For questions or concerns regarding the construction work, please contact the contractor’s public representative:

Elyse Shattuck
208.449.3377
TCS@Corridorcontractors.com

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or eraea@spokanecity.org.