West Plains to SIA Connection from Craig Road/McFarlane Road to Hayford Road/McFarlane Road

Project Number: 2015168

Construction Estimate: $1,900,000.00

Project Location: McFarlane Road between Hayford Road and Craig Road

Description: Install a new 12-inch ductile iron water main. The new line provides a connection between two pressure zones, the Plains and SIA, and provides circulation at the current dead-ends where the connection will take place. The alignment of the new water main will follow the alignment of the existing sewer main.

Status: Construction

Contractor: Halme Construction, Inc.

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Summer 2016

Substantially Completed Date: 05/25/2017

Award Date: June 13, 2016