Title 13 Public Utilities and Services
Chapter 13.03A Pretreatment
Article IV. Reporting Requirements
Section 13.03A.0402 Compliance Report Deadli
ne s – Initial Reports [4.2]
Deadline s.
Within the earliest applicable date of nine ty days following:
The date for final compliance of an existing significant industrial user with applicable pretreatment standards and requirements,
The date for final compliance in federal categorical standards, or
The date for final compliance set in a discharge permit; or
In the case of a ne w source or a ne w user determine d by the Plant Manager to fit the definition of a significant industrial user, within nine ty days following the commencement of discharge.
The affected user must submit to the Plant Manager a report as outline d in SMC 13.03A.0304(D) through (F) inclusive, and certified as provided in SMC 13.03A.0305(A) , Fees will be assessed in accordance with SMC 13.03A.1401 .
For users subject to equivalent mass or concentration limits established by the City in accord with 40 CFR 403.6(c), the report in subsection (A) of this section shall contain a reasonable measure of the user’s long term production rate. For all other users subject to categorical pretreatment standards expressed in terms of allowable pollutant discharge per unit of production (or other measure of operation), this report shall include the user’s actual production during the appropriate sampling period, and signe d as provided in SMC 13.03A.0305(A) . Fees will be assessed in accordance with SMC 13.03A.1401 .
NOTE: Bracketed enumerations reference the numbering in the EPA Region 10 Model Ordinance of March 27, 2012.
Date Passed: Monday, November 9, 2020
Effective Date: Wedne sday, December 16, 2020
ORD C35961 Section 39