Maple Ash Chipseal

Project Number: 2021095

Status: Construction

Construction Start Date: April 15, 2024

Estimated Completion Date: August 16, 2024

Contract Award Date:

Construction Estimate: $1,765,000.00

Contractor: Shamrock Paving, Inc.

Project Description

In the coming weeks, the City of Spokane will begin preparatory street maintenance work for a chip seal on Maple Street and Ash Street from Northwest Boulevard to Rowan Avenue. Chip seals are an important part of the City's street maintenance strategy. Please see the attached brochure for information on the process.

Project Highlights

The project encompasses various road surface improvements including:

  • Construction of approximately 65,000 square yards of chip seal.
  • Associated crack sealing.
  • Pavement repair.

Traffic Impact

Affected traffic routes will be announced prior to detours and road closures. Construction will take place in phases to reduce the impacts on traffic.

Note to Residents

If you have special access requirements for your property (such as business, medical, or disability), or general questions about this project, please contact the Construction Relations Manager or Contractor Public Representative. Additionally, if your property is in the city-owned path of construction and will be disturbed, you will receive a separate letter with more details prior to construction.

For everyone’s safety, please obey all traffic signs and check for traffic updates throughout the project.

Construction Zone Details

  • Planned Detours: Yes – as needed throughout construction
  • Planned Lane Restrictions: Yes – as needed throughout construction
  • Planned Road Closures: Yes – as needed throughout construction

Educational Materials


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor’s public representative.

Contractor Public Representative
Cody Rettke
codyr@shamrockpaving.us
509.385.3303

City Construction Relations Manager
Aaron Watts
awatts@spokanecity.org
509.992.4408

City Project Manager - Design Phase
Richard Proszek

City Project Manager - Construction Phase
Mike Zangara