***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 17D
Chapter 17D.020
Sections 17D.020.010...
 

Title 17D City-wide Standards

Chapter 17D.020 Financial Guarantees

Section 17D.020.010 Financial Guarantee

The director of engineering services may allow an applicant to establish a financial guarantee and obtain a certificate of occupancy or other permit or approval in advance of completing all required work or improvements if the following criteria are met:

  1. The applicant is unable to complete the work or improvements to be covered by the financial guarantee because of unavoidable circumstances that in no way resulted from the actions or inaction of the applicant; and/or
     
  2. It is reasonably certain that the applicant will be able to complete the work or improvements to be covered by the financial guarantee within a reasonable amount of time; and
     
  3. Granting the certificate of occupancy or other permit or approval prior to completion of the work or improvements will not be materially detrimental to the city or the properties in the vicinity of the subject property.

Date Passed: Monday, February 21, 2005

Effective Date: Wednesday, March 30, 2005

ORD C33582 Section 2

Section 17D.020.010 Financial Guarantee

The director of engineering services may allow an applicant to establish a financial guarantee and obtain a certificate of occupancy or other permit or approval in advance of completing all required work or improvements if the following criteria are met:

  1. The applicant is unable to complete the work or improvements to be covered by the financial guarantee because of unavoidable circumstances that in no way resulted from the actions or inaction of the applicant; and/or
     
  2. It is reasonably certain that the applicant will be able to complete the work or improvements to be covered by the financial guarantee within a reasonable amount of time; and
     
  3. Granting the certificate of occupancy or other permit or approval prior to completion of the work or improvements will not be materially detrimental to the city or the properties in the vicinity of the subject property.

Date Passed: Monday, February 21, 2005

Effective Date: Wednesday, March 30, 2005

ORD C33582 Section 2