***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 17D
Chapter 17D.090
Sections 17D.090.070...
 

Title 17D City-wide Standards

Chapter 17D.090 Erosion and Sediment Control

Section 17D.090.070 Plan Required
  1. A responsible party must submit an erosion and sediment control (ESC) plan or a Stormwater Pollution Prevention Plan (SWPPP) for permitted development projects to the Director of Wastewater Management for review.
    1. An ESC is required if the disturbance area is:
  1. five thousand square feet or greater in area;
  1. in a special site per SMC 17D.090.080.
    1. A SWPPP is required and must be fully implemented in accordance with the Construction General Stormwater Permit if the disturbance area is:
  1. one acre or more; or
  1. is a construction project less than one acre that is part of a larger common plan of development or sale.
  1. An ESC plan or SWPPP is not required for work that does not require a City issued permit unless otherwise required by the terms of a compliance order or land use decision.
  1. Where a plan is required, the responsible party shall not commence any construction before the Director of Wastewater Management has accepted the proposed plan.

Date Passed: Monday, October 25, 2021

Effective Date: Thursday, December 2, 2021

ORD C36116 Section 6

Section 17D.090.070 Plan Required
  1. A responsible party must submit an erosion and sediment control (ESC) plan or a Stormwater Pollution Prevention Plan (SWPPP) for permitted development projects to the Director of Wastewater Management for review.
    1. An ESC is required if the disturbance area is:
  1. five thousand square feet or greater in area;
  1. in a special site per SMC 17D.090.080.
    1. A SWPPP is required and must be fully implemented in accordance with the Construction General Stormwater Permit if the disturbance area is:
  1. one acre or more; or
  1. is a construction project less than one acre that is part of a larger common plan of development or sale.
  1. An ESC plan or SWPPP is not required for work that does not require a City issued permit unless otherwise required by the terms of a compliance order or land use decision.
  1. Where a plan is required, the responsible party shall not commence any construction before the Director of Wastewater Management has accepted the proposed plan.

Date Passed: Monday, October 25, 2021

Effective Date: Thursday, December 2, 2021

ORD C36116 Section 6