***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 17D
Chapter 17D.090
Sections 17D.090.170...
 

Title 17D City-wide Standards

Chapter 17D.090 Erosion and Sediment Control

Section 17D.090.170 Maintenance

The requirements of this section apply to all permitted ground-disturbing activities.

  1. The responsible party shall maintain all erosion and sediment control measures, temporary and permanent, in proper functioning order.
     
  2. The responsible party shall inspect, maintain, adjust, repair, and replace erosion and sediment control measures within twenty-four hours following a storm event to ensure that the measures are functioning properly.
     
  3. During active ground-disturbing activity, the responsible party shall inspect and maintain erosion and sediment control measures daily between October 1 and April 30.
     
  4. All inspections conducted by a responsible party in subsections (B) and (C) above shall be noted in an inspection log indicating the date and time of the inspection. Copies of the inspection log shall be made available to the director upon request.

Date Passed: Monday, March 8, 2010

Effective Date: Sunday, April 11, 2010

ORD C34565 Section 1

Section 17D.090.170 Maintenance

The requirements of this section apply to all permitted ground-disturbing activities.

  1. The responsible party shall maintain all erosion and sediment control measures, temporary and permanent, in proper functioning order.
     
  2. The responsible party shall inspect, maintain, adjust, repair, and replace erosion and sediment control measures within twenty-four hours following a storm event to ensure that the measures are functioning properly.
     
  3. During active ground-disturbing activity, the responsible party shall inspect and maintain erosion and sediment control measures daily between October 1 and April 30.
     
  4. All inspections conducted by a responsible party in subsections (B) and (C) above shall be noted in an inspection log indicating the date and time of the inspection. Copies of the inspection log shall be made available to the director upon request.

Date Passed: Monday, March 8, 2010

Effective Date: Sunday, April 11, 2010

ORD C34565 Section 1