***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 17G
Chapter 17G.030
Sections 17G.030.040...
 

Title 17G Administration and Procedures

Chapter 17G.030 Design Departures

Section 17G.030.040 Decision Criteria

The decision criteria for a design departure are provided below.

  1. Has the applicant’s design team thoroughly examined how the Requirement (R) and/or Presumption (P) could be applied as written?
  1. Does the proposal meet the intent and the general direction set forth by the Requirement (R) and/or Presumption (P) as written?
  1. For a Requirement (R), is the specific change superior in design quality to that potentially achieved by the Requirement as written?
  1. For a Presumption (P) is the specific change equal to or superior in design quality to that potentially achieved by the Presumption as written?
  1. Is the departure necessary to better address aspects of the site or its surroundings?
  1. Is the proposed departure part of an overall, thoughtful and comprehensive approach to the design of the project as a whole?
  1. Has the applicant responded to the optional Considerations (C), if any, found within the design guideline? Including Considerations may assist in gaining acceptance for the plan.

Date Passed: Monday, November 20, 2023

Effective Date: Monday, January 1, 2024

ORD C36459 Section 32

Section 17G.030.040 Decision Criteria

The decision criteria for a design departure are provided below.

  1. Has the applicant’s design team thoroughly examined how the Requirement (R) and/or Presumption (P) could be applied as written?
  1. Does the proposal meet the intent and the general direction set forth by the Requirement (R) and/or Presumption (P) as written?
  1. For a Requirement (R), is the specific change superior in design quality to that potentially achieved by the Requirement as written?
  1. For a Presumption (P) is the specific change equal to or superior in design quality to that potentially achieved by the Presumption as written?
  1. Is the departure necessary to better address aspects of the site or its surroundings?
  1. Is the proposed departure part of an overall, thoughtful and comprehensive approach to the design of the project as a whole?
  1. Has the applicant responded to the optional Considerations (C), if any, found within the design guideline? Including Considerations may assist in gaining acceptance for the plan.

Date Passed: Monday, November 20, 2023

Effective Date: Monday, January 1, 2024

ORD C36459 Section 32